The Design and Build Contracts are awarded subject to preparation of a bespoke Works Order (WO) Application process involving a high degree of preparation including:- notification, stakeholder management and safety, health, quality and environmental planning working in close partnership with NI Water’s Project Management Team. Five Works packages concentrating in East Belfast, each averaging 200 replacements were delivered in 2018 and 2019 in the Ravenscroft Avenue, Kirkliston Park, Willowholme, Orby Drive and Castledona Crescent areas of the city.Nu Line Utilities approach to the work was to deploy a highly skilled ten person team delivering high productivity installation of 50 to 65 replacements per week, rapid commissioning and right on time permanent reinstatement and handover.
The programme continues and Córas welcome inquiries from prospective clients across Ireland in relation to solutions to their Lead Pipe Replacement challenges.